Timetable
October 2009:
Planning Permit Application lodged with the
Responsible Authority.
March 2010 - April 2010:
Public Exhibition of Planning Permit Application
documentation until Tuesday 27th April 2010.
July 2010:
The Panel Hearing process was completed on the 15th July 2010.
October 2010:
RES received planning permits from both Councils on Friday
22nd of October 2010 from the then Minister for Planning,
Hon Justin Madden.
Third Quarter 2011:
Lodging both planning applications for the external
overhead line with Ararat Rural City Council and Pyrenees Shire
Council.
![]() |
![]() |
![]() |
![]() |